Vegetation Removal from Rail Road Bridge and Footbridge
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Home | Re-Padding Track
“Rail Projects were delighted to be able to assist Network Rail with this project, and our successful completion of the job under PCL conditions with an on-site audit is a testament to the hard work of the team, our expertise and our commitment to safety.”
Network Rail required the re-padding of 250 yards of track on both legs for their PAD Lichfield project but had delays due to other work commitments. RSSI was the Principal Contractor for the project, providing Possession planning, CPP, WPP, Task Briefs, AMP10 walkout, Handback, and safety-critical staff to complete the job within two nights on a project worth £30K.
Location
Lichfield
Project Value
£30,000
Division
Rail Operations
Project Duration
3 Days
This Rail Projects project required repadding 250 yards of track on both legs to address the excessive wear on the track. The client, Network Rail, could not complete the project due to other work commitments. RSS was appointed as the project’s principal contractor, meaning they had to run it from start to finish.
To complete the project, RSSI provided Possession planning, CPP, WPP, Task Briefs, AMP10 walkout, Handback, and safety-critical staff, including ES, COSS, Supervisor, STM, CRE, and CEM. The project was completed within two nights, and the project value was £30K.
One of the challenges was that this was RSSI’s first job under PCL conditions with an on-site audit. However, they successfully passed the audit without any non-conformances, demonstrating their expertise and commitment to safety.
Overall, RSSI completed a piece of work that the client could not complete due to their work commitments and completed it safely and efficiently, passing the PCL audit with flying colours.
RSS Infrastructure (RSSI), based in Birmingham, Cwmbran, Doncaster and Tonbridge, provides infrastructure services for the rail, civil, and utilities sectors. We serve clients like Network Rail, WMCA, HS2 and Tier 1 & 2 contractors. Our services include Arboriculture, Civils and Construction, Geofencing, Industrial Rope Access (IRATA), Magnetic Track Safety, Rail Operations including Possession Management and P/Way, Rail Welding, Signalling, and Track Warning Services.
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Taziker was awarded a contract to replace life-expired wheel timbers on a series of bridges in the Manea area between Ely and March.
Welding S&C Unit was contracted to work on Phase 2 of the Birmingham Midland Metro Alliance or MMA Westside Extension.