Vegetation Removal from Rail Road Bridge and Footbridge
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Home | ECM8 Track Renewal System
“TWS has planned and designed six ATWS sites installed, operated and recovered in line with the agreed ECM8 Track Renewal programme. The project has been managed on-site by Moyna Bateman.”
Network Rail’s High Output team in Newcastle has been assigned to perform TRS track renewals on ECM8 in Scotland. The TRS technology can renew a quarter-mile of track overnight, but the work cannot be carried out without deploying a Track Warning System to ensure the safety of the workers.
Location
Newcastle
Project Value
£133,966
Division
Track Warning Services
Project Duration
9 Weeks
The Track Renewal System (TRS) is capable of renewing a quarter mile of track overnight, making it ready for morning commuters. This is done by using the TRS machine during the night, while High Output takes possession of the line. However, this poses a significant risk to the worksite, as the adjacent line remains open to trains. Therefore, Network Rail High Output Newcastle cannot carry out the track renewal works without a Track Warning System (TWS) being deployed.
To address this concern, the RSSI Track Warning Services (TWS) department designed and implemented six Schweizer LYNX ATWS sites, which are installed, operated, and recovered in line with the agreed program.
Moyna Bateman has led this project on-site, relocating to Scotland for its duration. The Schweizer LYNX equipment’s radiographic feature has enabled the installation and recovery of the sites with fewer human resources, reducing travel requirements from Birmingham to Scotland.
The RSSI TWS had to remain flexible with the installation and recovery plan to enable Network Rail High Output Newcastle to over or underachieve their works every week. Newcastle High Output has been able to deliver their Track Renewal System core works with the assurance that staff will receive an audible and visual warning of any approaching trains.
Overall, the implementation of the Track Renewal System and the Track Warning System has significantly improved the safety and efficiency of railway track renewal works.
RSS Infrastructure (RSSI), based in Birmingham, Cwmbran, Doncaster and Tonbridge, provides infrastructure services for the rail, civil, and utilities sectors. We serve clients like Network Rail, WMCA, HS2 and Tier 1 & 2 contractors. Our services include Arboriculture, Civils and Construction, Geofencing, Industrial Rope Access (IRATA), Magnetic Track Safety, Rail Operations including Possession Management and P/Way, Rail Welding, Signalling, and Track Warning Services.
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Taziker was awarded a contract to replace life-expired wheel timbers on a series of bridges in the Manea area between Ely and March.
Welding S&C Unit was contracted to work on Phase 2 of the Birmingham Midland Metro Alliance or MMA Westside Extension.
Copyright © 2024 RSS Infrastructure Ltd.
Company Registration No. 06278727
Get notified about new articles