RSS Infrastructure (RSSI), a subsidiary of Auctus Management Group Ltd, have been working alongside Colas Rail to help improve productivity and safety for their workforce at their site in Wembley North where the client was conducting Plain Line Renewals in addition to installing Switches and Crossovers (S&C).
RSSI Track Access team conducted an initial survey to scope the worksite and identify areas where they could improve safety, efficiency and productivity. The team found that currently the site only had one point of access as well as limited room for storage access and welfare facilities. Furthermore, the RSSI Arboriculture (Arb) teams also identified the site walking route was dangerous and inaccessible to personnel due to thick vegetation and existing tree stumps as well as the uneven terrain that could cause tripping hazards and would also hamper the works being conducted by the Track Access team.
The Arboriculture site survey identified that the project would consist of three key phases namely; removal of vegetation, stump removal and herbicide treatment. Due to the work being more than 3 metres away from the nearest live line the teams were able to work during mid-week days under the supervision of a Safe Work Leader 1. The Arb team began by setting up an exclusion zone around the immediate work area and conducted a thorough assessment of the area using a CAT scanner to identify any S&C cables.
In order for the RSSI Track Access team to lay the foundations for the footpath, Arb personnel needed to firstly remove approximately 1km of thick vegetation and trees that needed to be felled and removed to enable access.
All personnel that were assigned to the project had a minimum of;
To ensure that project was completed in the required timeframe RSSI Arboriculture & Vegetation Management deployed a team of 5 consisting of;
The next phase was to eradicate all tripping hazards caused by existing stumps and vegetation. The team used Stump Grinders to take each stump down to ground-level where there was sufficient safe access to do so. In areas that had limited clearance, Arb personnel were required to manually remove each stump. The final phase was to then treat the entire area with Herbicide to control regrowth.
Working alongside the client, Track Access division began by installing 450 metres of rubber zap mats in order to create a safe authorised walking route. The RSSI team then fitted a single pedestrian access gate at both the North and South hard standings.
In order to improve working conditions, a welfare facility was constructed at each hard standing. These welfare facilities gave Colas the capability to further enhance their own efficiency and safety through the creation of an observation tower that sat on top of the welfare building.
From the initial project survey, the RSSI Track Access planning team identified that there was another potential hazard stemming from the electrified cables as well as workers straying from the authorised walking route. To prevent the likelihood of an accident or incident occurring, RSS teams implemented 450 metres of ‘Plastic Thermos Barriers’ whose non-conductive material makes it ideal for areas that contain electrification and also acts as a barrier to keep personnel on the right track.
To increase both safety and productivity, four Strail Road Rail Access Points (RRAPS) were installed to improve access for rail road access vehicles. Three RRAPS were installed north of the worksite, enabling machinery to gain access to the works and crossover safely.
Working alongside the client, Track Access division began by installing 450 metres of rubber zap mats in order to create a safe authorised walking route. The RSSI team then fitted a single pedestrian access gate at both the North and South hard standings.
In order to improve working conditions, a welfare facility was constructed at each hard standing. These welfare facilities gave Colas the capability to further enhance their own efficiency and safety through the creation of an observation tower that sat on top of the welfare building.
From the initial project survey, the RSSI Track Access planning team identified that there was another potential hazard stemming from the electrified cables as well as workers straying from the authorised walking route. To prevent the likelihood of an accident or incident occurring, RSS teams implemented 450 metres of ‘Plastic Thermos Barriers’ whose non-conductive material makes it ideal for areas that contain electrification and also acts as a barrier to keep personnel on the right track.
To increase both safety and productivity, four Strail Road Rail Access Points (RRAPS) were installed to improve access for rail road access vehicles. Three RRAPS were installed north of the worksite, enabling machinery to gain access to the works and crossover safely.
Through the introduction of welfare facilities, Colas were able to improve their workforce productivity as they were no longer required to commute long distances. These facilities provided senior Colas personnel with an opportunity to increase visibility and improve safety and productivity through the additional observation tower that was constructed by the client.
Furthermore, through the efforts employed by the RSSI Arb team, who complete the vegetation and stump removal in two weeks, the RSSI Track Access team was able to install an authorised walking route, RRAPS, access gate and the Thermos barrier enabling the workforce at Wembley North to reduce deployment times for machinery and personnel through increased levels of safe access.
Jamie Gibbons, Site Manager for S&C South Alliance, said: “The de-vegetation works that the RSSI team undertook were to a very high standard, the site looks 100% better and everybody was really happy with the service the company provided.”
The project was delivered in accordance with the clients’ work schedule and also came in on budget.
“RSSI personnel who were involved with the works at Northam had to work through some of the worst weather conditions I have seen and continued to keep spirits high and had a fantastic work attitude allowing for the project to continue.”
Chris Courtenay – Signalling Supervisor (Infrastructure) for Colas Rail“Thanks to RSSI we are on top of all movements every day with nothing outstanding. ”
Ryan Steel – Field Engineer (OLE England) at Amey“RSSI assisted in the cable running shifts, preparation work including changeovers of the 8 x track circuits and the 10c, 27c and 4 x 48c lineside cables. Their quality of work, attitude and work ethic has been absolutely spot on. ”
Dan Palmer – Installation and Construction Engineer at Carillion Signalling“Being able to work during the day with trains still running is fantastic for team fatigue. The use of an ATWS installed for the duration makes the job even safer and removes the need for Lookouts. Thanks to the guys from RSSI for installing and managing for us.”
Robert Woods – Senior Project Manager at Amey“The RSSI personnel who worked on the Bilston Road Track Renewal project have been exceptional and played a major part in ensuring the works were completed on time and to budget.”
Paul Brown – Project Director for Midland Metro Alliance“The De-Veg works that the Arboriculture team undertook was to a very high standard, the site looks 100% better and everybody my end is really happy with the service you provided. ”
Jamie Gibbons – Site Manager for S&C Alliance“I have had a good walk along the fence line and I am very happy with the work carried out. All the over hanging trees and Limbs have been removed. Very good work. ”
Mike Gibson – Terminal Manager for Associated British PortsRSS Infrastructure Ltd (RSSI) has been awarded the Social Value for Future Generations award in the Social Value Portal 2021 Awards.
Read MoreRSS Infrastructure (RSSI), a leading provider of services to infrastructure businesses across the UK, recently received the esteemed “GOLD” standard from Supply Chain Sustainability School – an organisation that awards excellence in sustainable business practices. Every year, the infrastructure sector is estimated to produce 720 million tonnes of building, demolition, and excavation waste in the..
Read MoreRecently we spoke with David White, Group HSQE Manager, about how he aims to strengthen the safety culture at Auctus Management Group and its member firms, RSS Infrastructure and INFRA Skills, and his overall safety vision. David has identified nine key points to improving safety culture, summarised below. An excellent safety culture requires strong leadership..
Read MoreCompany Registration No. 06278727