“We were impressed with the team’s dedication and professionalism on the Warrington Power Station project. They overcame challenges and delivered the project within the given timeline and budget. The solution provided was effective, and we appreciate their hard work. We would recommend their services to others.”
Rob Leland, Ridge
Services Delivered
This Rail Projects project involved examining a private third-party owned structure for the client. The inspection report aimed to determine whether heavier vehicles could be used across the structure, which would increase productivity. The solution provided included several aspects; supplying a team including a COSS and bridge examiners, suppling PASMA towers, organising line blocks and the supply of a road over rail crane. To facilitate the examination, a road closure was organised to the plant.
Key Actions
- Organising a road closure to the plant
- Providing a team, COSS and bridge examiners
- Supplying PASMA towers and a road over rail crane
- Examining a private third-party owned structure for the client
- Determining whether heavier vehicles could be used across the structure
- Closing the bridge to the power station
- Organising line blockages and sidings possession
- Obtaining third-party land owners’ agreements
Project Delivery
Ridge was the client for the Warrington Power Station project, which had a value of £6k and a duration of one week. The project involved examining a private thirdparty owned structure for the client. The examination aimed to determine whether heavier vehicles could be used across the structure, which would increase productivity.
To facilitate the examination, a road closure was organised to the plant. The solution provided included a team, COSS, PASMA towers, line blocks, road closure, bridge examiners, and supply road over rail crane.
The bridge to the power station had to be closed, and line blockages and sidings possession had to be organised. Third-party land owners’ agreements had to be obtained.
This was a challenging project to gain all stakeholder buy-in and agreements. However, the team successfully delivered the project within the given timeline and budget.