Vegetation Removal from Rail Road Bridge and Footbridge
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Home | SATWS for Network Rail Newcastle DU
“The SATWS we delivered allowed the team to carry out their works during daylight and while trains were running. They were guaranteed to work as and when they needed without the risk of line blockages being cancelled or offered for very short durations.”
Network Rail Newcastle DU’s maintenance team needed to regularly inspect their section track and junctions for wear/tear and damage to ensure safe passage of trains all year round. Due to the high passage of trains on ECM5, there were limited opportunities to take line blockages. Daytime patrols were needed, but an ORR improvement order removed the unassisted lookout option. The work was either falling behind or being pushed to nights, which wasn’t ideal for detailed examinations. RSSI were tasked with providing a treadle-based Track Warning solution that allowed Network Rail to continue their works during the hours of daylight. Initially, this was going to be an ATWS system, but the amount of resource and time required to install and recover proved to be disproportionate for the works. The TWS department then decided on a ZOLLNER GB2 Semi Automatic Track Warning System SATWS.
Location
Newcastle
Project Value
£224,000
Division
Track Warning Systems
Project Duration
Rolling 16 weeks plan
TWS Planning created 18 unique SATWS designs covering both lines on ECM5. Due to signalling in the area, trains could travel in either direction on both lines, making the SATWS more challenging to design and operate. The TWS Planning department took the decision to work with the Tyneside signal box to create a Straight-Line Running Procedure (SLRP) negating the need to cover wrong direction moves.
TWS Planning had to work with Tyneside signalling to simplify the running of trains on ECM5; otherwise, the SATWS would have been too difficult to use efficiently. RSSI came up with an SLRP, and the 16-week rolling plan was agreed upon, with three sites installed and recovered every week. The SATWS allowed the teams to carry out their works during daylight
and while trains were running. The system guaranteed to work as and when
needed without the risk of line blockages being cancelled or offered for very short durations. The project has been running since 2019.
RSS Infrastructure (RSSI), based in Birmingham, Cwmbran, Doncaster and Tonbridge, provides infrastructure services for the rail, civil, and utilities sectors. We serve clients like Network Rail, WMCA, HS2 and Tier 1 & 2 contractors. Our services include Arboriculture, Civils and Construction, Geofencing, Industrial Rope Access (IRATA), Magnetic Track Safety, Rail Operations including Possession Management and P/Way, Rail Welding, Signalling, and Track Warning Services.
RSS Infrastructure (RSSI) undertook a challenging project to remove vegetation from a railway road bridge and a footbridge.
Taziker was awarded a contract to replace life-expired wheel timbers on a series of bridges in the Manea area between Ely and March.
Welding S&C Unit was contracted to work on Phase 2 of the Birmingham Midland Metro Alliance or MMA Westside Extension.
Copyright © 2024 RSS Infrastructure Ltd.
Company Registration No. 06278727
Get notified about new articles