Feltham Train Depot

“The expertise and support provided by RSS Infrastructure were instrumental in ensuring that the Feltham Train Depot signalling project was completed on time and to the highest standards.”
Fenix Rail Systems

Services Delivered

Fenix Rail Systems was tasked with installing a depot control system and point machines at the Feltham Train Depot. The original contractor fell behind schedule, prompting Fenix to seek help from RSS Infrastructure to complete the installation, testing, and commissioning of the equipment. RSS Infrastructure provided a Test Strategy and Test Plan, an installation team, and a testing team to complete the work and ensure the equipment was brought into use earlier than proposed.

Key Actions

  • RSS Infrastructure provided a TIC to create and implement a Test Strategy
    and Test Plan.
  • Supplied an installation team to complete the remaining installation
    works.
  • Supplied a testing team to rectify issues discovered during testing and
    commissioning.
Signalling_
location-icon

Location

Feltham

Werrington Grade Separation, RSS Infrastructure

Project Value

£14,921.27

Werrington Grade Separation, RSS Infrastructure

Division

Signalling

Werrington Grade Separation, RSS Infrastructure

Project Duration

9 Days

Project Delivery

Fenix Rail Systems was awarded the contract to install a bespoke depot control system and point machines at the Feltham Train Depot. However, the original contractor hired to carry out the work was behind schedule, which threatened to delay the project completion.

To ensure that the project was completed on time and to the highest standards, Fenix Rail Systems approached RSS Infrastructure to take over the installation, testing, and commissioning of the equipment. RSS Infrastructure provided a Test Strategy and Test Plan, which included the creation and implementation of a comprehensive testing plan, to ensure that the equipment was functioning as intended.

RSS Infrastructure also supplied an installation team to complete the remaining installation works and a testing team to identify and rectify any issues discovered during the testing and commissioning phase.

As a result of the expertise and support provided by RSS Infrastructure, the Feltham Train Depot signalling project was completed ahead of schedule.

The client was able to bring the depot equipment into use earlier than proposed by the original contractor, saving time and money while ensuring that the signalling system was functioning as intended.

About Us

RSS Infrastructure provides multi-disciplinary infrastructure services for the rail, civil and utilities sectors. With offices in Birmingham, Cwmbran, and Doncaster, RSSI works with several clients, including Network Rail, WMCA, Midland Metro Alliance, HS2 as well as Tier 1 & 2 contractors. Services offered include; Arboriculture, Construction & Civils, Magnetic Track Safety, Possession Management, Rail Operations, Safety-Critical Resource, Signalling, Track Warning Services, and Welding.

Projects

York Tram Line
Welding

York Place to Newhaven Extension

“The complexities of this project presented significant challenges, from inexperienced subcontractors to unforeseen circumstances like COVID-19. However, our dedicated and experienced team at RSSI delivered

Read More »
Nottingham Tram Extension
Welding

Nottingham Tram Extension

“Through our collaboration with the civil teams and leveraging our extensive experience within the light rail sector, we were able to overcome significant obstacles, accelerate

Read More »
Receive the latest news

Subscribe To Our Newsletter

Get notified about new articles