Services Delivered

RSSI’s Civils & Construction division worked with Taziker who were carrying out improvements on bridges in the area. The main issue for the client was poor access to the worksite so we installed multiple RRAPs.

Key Actions

  • 6 x RRAPs installed
  • Created multiple access points
  • Worked to a limited timeframe
  • Improved access to worksites
manea-bridge-alt
location-icon

Location

Cambridgeshire

Werrington Grade Separation, RSS Infrastructure

Project Value

£18,000

Werrington Grade Separation, RSS Infrastructure

Division

Civils & Construction

Werrington Grade Separation, RSS Infrastructure

Project Duration

3 Weekends

Project Delivery

Our team created access points on both sides of the bridge. We installed track crossing points at the bridge entrance to allow heavy plant to cross the track when required. Our primary aim was to ensure safe access and improve productivity for the Taziker staff carrying out the bridge improvements in the area.

One of the challenges we faced was access to the site as it was very remote. After we installed the first access point, the installation team had the problem of how to reach the remaining RRAPS. Working together with Taziker, we were able to arrange an RRV to take the required materials to the site. Taziker completed the access road up to the boundary fence.

The team installed an additional four RRAPs at various points to further improve access. The successful completion allowed improved access to remote areas and gave more flexibility to working times and productivity.

We completed the project over 3x weekend shifts. The works were completed and delivered in line with the time and budgetary requirements. It was possible to provide the client with real-time insight into the inspection. RSS Infrastructure utilised a mobile application that provided the client with shift reports while on site. These reports also included visual evidence of the works. The images were uploaded into cloud storage for multiple users to gain access.

About Us

RSS Infrastructure provides multi-disciplinary infrastructure services for the rail, civil and utilities sectors. With offices in Birmingham, Cwmbran, and Doncaster, RSSI works with several clients, including Network Rail, WMCA, Midland Metro Alliance, HS2 as well as Tier 1 & 2 contractors. Services offered include; Arboriculture, Construction & Civils, Magnetic Track Safety, Possession Management, Rail Operations, Safety-Critical Resource, Signalling, Track Warning Services, and Welding.

Projects

York Tram Line
Welding

York Place to Newhaven Extension

“The complexities of this project presented significant challenges, from inexperienced subcontractors to unforeseen circumstances like COVID-19. However, our dedicated and experienced team at RSSI delivered

Read More »
Nottingham Tram Extension
Welding

Nottingham Tram Extension

“Through our collaboration with the civil teams and leveraging our extensive experience within the light rail sector, we were able to overcome significant obstacles, accelerate

Read More »
Receive the latest news

Subscribe To Our Newsletter

Get notified about new articles