L2C & K2C Renewal Works

“The collaboration between RSSI and Amey Rail Projects was aimed at ensuring the hand back package was fully compliant with Network Rail standards by completing stress testing on each section and documenting renewal activity.”
Karl Dean, Head of Welding

Services Delivered

RSS Infrastructure (RSSI) Welding collaborated with Amey Rail Projects on a three-year contract to assist in the delivery of the L2C & K2C renewal works between Bedford, Kettering & Corby. The primary objective of the project was to complete stress testing required for the finalisation of records relating to each section and renewal activity and to ensure that the hand back package was fully compliant with Network Rail standards.

Key Actions

  • RSSI and Amey Rail Projects worked together for three years on L2C & K2C renewal works
  • RSSI completed stress testing and used the Verse monitoring system to measure SFT of CWR
  • The team included 5 Skilled Track Operatives, 1 Controller of Site Safety & 1 Verse Engineer, with tools & equipment
  • Two tests were carried out over 8 midweek night shifts under four-hour possessions
  • All certification produced by Verse technology was signed off as part of the hand back package
L2C & K2C Renewal Works
location-icon

Location

Bedford, Kettering & Corby

L2C & K2C Renewal Works, RSS Infrastructure

Project Value

N/A

L2C & K2C Renewal Works, RSS Infrastructure

Division

Welding

L2C & K2C Renewal Works, RSS Infrastructure

Project Duration

3 Years

Project Delivery

The main challenge for the project was to establish an accurate Stress-free temperature (SFT) measurement for the Continuous Welded Rails (CWR). Additionally, the project required a skilled team to carry out the tests over multiple night shifts while ensuring compliance with safety regulations.

To overcome the challenges, RSSI utilised the Verse monitoring system to establish an accurate SFT measurement for the CWR. The team consisted of a 5x Skilled Track Operatives, 1x Controller of Site Safety & 1x Verse Engineer as well as tools & equipment.

The Verse technology provided a non-intrusive and reliable method of measuring the SFT of the CWR.

This allowed for accurate stress testing of the rails, ensuring that the final records and hand back package were fully compliant with Network Rail standards.

Two tests were carried out over 8x midweek night shifts under four-hour possessions. All certification produced by the VERSE technology was signed off as part of the hand back package.

The collaboration between RSSI and Amey Rail Projects was successful in delivering the L2C & K2C renewal works, meeting all safety regulations and Network Rail standards. The accurate stress testing provided by the Verse technology helped ensure the longevity of the rail infrastructure and a safe and efficient rail service for years to come.

About Us

RSS Infrastructure provides multi-disciplinary infrastructure services for the rail, civil and utilities sectors. With offices in Birmingham, Cwmbran, and Doncaster, RSSI works with several clients, including Network Rail, WMCA, Midland Metro Alliance, HS2 as well as Tier 1 & 2 contractors. Services offered include; Arboriculture, Construction & Civils, Magnetic Track Safety, Possession Management, Rail Operations, Safety-Critical Resource, Signalling, Track Warning Services, and Welding.

Projects

York Tram Line
Welding

York Place to Newhaven Extension

“The complexities of this project presented significant challenges, from inexperienced subcontractors to unforeseen circumstances like COVID-19. However, our dedicated and experienced team at RSSI delivered

Read More »
Nottingham Tram Extension
Welding

Nottingham Tram Extension

“Through our collaboration with the civil teams and leveraging our extensive experience within the light rail sector, we were able to overcome significant obstacles, accelerate

Read More »