BACKGROUND – AN OVERVIEW OF THE CURRENT SITUATION

With the constant pressure to complete the Great Western Electrification Project, RSSI was approached to assist in delivering a cost effective solution to complete packages of work and hence allowing the projects main construction teams to progress along the routes.

SOLUTION

RSS Infrastructure Ltd (RSSI) was able to offer construction support to the GWEP programme by providing a package solution alongside our industry partners consisting of Safety Critical Staff, OLEC Staff (trainee linesman to handback engineer), Plant and all required tools and equipment.

Works ranged from packages of installation to snagging works to ensure that the programme was able to meet its deadlines for energisation.

CONCLUSIONS / RESULTS – WHAT BENEFIT WAS THIS FOR THE CLIENT

As a result of the works, RSSI has been able to ensure a good relationship with its clients by providing a tailored solution to every situation, with confidence to the client that the works are of the highest quality.

Meet the Expert

Josh Cook

Meet the expert

“RSSI personnel who worked to recover the IBJ’s were faultless and brilliant guys to work with, they are a credit to the S&T division at RSSI.”

Brian Watterson – Signalling Supervisor Phase 5 at S&C North Alliance

“RSSI personnel who were involved with the works at Northam had to work through some of the worst weather conditions I have seen and continued to keep spirits high and had a fantastic work attitude allowing for the project to continue.”

Chris Courtenay – Signalling Supervisor (Infrastructure) for Colas Rail

“I would like to thank RSS for their work so far on the blockade at Northam, they have been great.”

Andrew Woolliss – Project Engineer (Wessex) S&C – Infrastructure

“Thanks to RSSI we are on top of all movements every day with nothing outstanding. ”

Ryan Steel – Field Engineer (OLE England) at Amey

“RSSI assisted in the cable running shifts, preparation work including changeovers of the 8 x track circuits and the 10c, 27c and 4 x 48c lineside cables. Their quality of work, attitude and work ethic has been absolutely spot on. ”

Dan Palmer – Installation and Construction Engineer at Carillion Signalling

“Being able to work during the day with trains still running is fantastic for team fatigue. The use of an ATWS installed for the duration makes the job even safer and removes the need for Lookouts. Thanks to the guys from RSSI for installing and managing for us.”

Robert Woods – Senior Project Manager at Amey

“The RSSI personnel who worked on the Bilston Road Track Renewal project have been exceptional and played a major part in ensuring the works were completed on time and to budget.”

Paul Brown – Project Director for Midland Metro Alliance

“The RSSI Arboriculture Team did a great job in completing the job safely and efficiently as planned. The feedback from my site supervisor was very good, he said that all exclusion zone were enforced and adhered to and appropriate PPE was used for the task. ”

Ameer Ibrahim – Senior Project Manager for Colas

“The De-Veg works that the Arboriculture team undertook was to a very high standard, the site looks 100% better and everybody my end is really happy with the service you provided. ”

Jamie Gibbons – Site Manager for S&C Alliance

“I have had a good walk along the fence line and I am very happy with the work carried out. All the over hanging trees and Limbs have been removed. Very good work. ”

Mike Gibson – Terminal Manager for Associated British Ports

Infrastructure Solutions

  • Overhead Line Electrification
  • Track Warning Services
  • Welding
  • Signalling Services
  • Resource & Recruitment
  • Recruitment
  • Construction & Civils
  • Magnetic Track Safety Solutions
  • Track Access & Lighting
  • Vegetation Management
View Solutions

Selected News

Team Auctus Complete Pedal To Paris 2021

On Sunday 6th September 2021 ‘Team Auctus’, consisting of Richard Toy, Sean Harrison, Andrew Coates, John Handley, Martin Benson, Simon Capper, Graham Talbot, John McDonough, Steve Broadfield and Ryan Spence completed the Pedal To Paris 2021 challenge. The premier cycling event was hosted by The Royal British Legion charity, to coincide with their 100 years..

Read More

RSS Infrastructure Ltd Celebrates Commitment To Railway Mental Health Charter

Auctus Management Group Ltd, and subsidiary companies RSS Infrastructure Ltd and INFRA Skills Ltd has signed the Railway Mental Health Charter to support the reduction of mental health stigma and change behaviours in the workplace, through cross industry collaboration. The Railway Mental Health Charter is a framework to help rail companies promote, manage and support..

Read More

RSS Infrastructure

RSS Infrastructure are focused on increasing productivity and improving safety across the UK’s infrastructure. By working with you, as your trusted partner, we will provide a range of tailored infrastructure services and safety products you can count on.

Contact

Subscribe

Apply Online

    X